Critical Spare Parts Stock

Gains:

  • Can separate critical part from ordinary part
  • Can determine stock level according to lead time
  • Plans stock strategy in export projects

Stockpiling each item binds capital; not stocking any stops production. The correct approach is to classify the part by two criteria: failure outcome and lead time.

Classification

Critical part: when it breaks down, the plant stops and its supply takes a long time. Example: specially sized roller bearing, main drive motor, plansifter suspension element.

Important part: when it breaks down, capacity drops but production does not stop; The supply is medium term.

Ordinary part: quickly available from local market; There is no need to stock up.

In export projects

In a facility abroad, the supply time increases to weeks, including customs. That's why the first set of critical parts is included in the commissioning package; "Why these are necessary" is clearly explained to the customer.

Prepare the spare parts list for the facility. The overall list creates either overstock or understock; Neither of them pleases the customer.